DCV Evolution-Release

DCV Evolution News N° 30 "The DCVe Platform Rehearsal for Moving into Production comes to an End"

Dear Depositors,

At DCV, we have completed a new rehearsal for moving into production in the DCVe Platform. We would like to thank the 89 companies and more than 500 DCVe operators that participated actively in the tests.

This rehearsal, which is critical for the activities before the DCVe start of services scheduled on June 20, 2022, could not have been possible without the continuous commitment of all of our depositors and operators.

In this context, DCV would like to highlight the following:

  • The rehearsal for participating depositors has concluded at the end of the day on Tuesday, May 17, 2022.
  • All the activities, configurations, transactions, etc., conducted on Monday, May 16, and Tuesday, May 17, will be removed from the DCVe production environment https://dcvevolucion.dcv.cl, and will go back to their previous status of Friday, May 13.
  • The DCVe production environment https://dcvevolucion.dcv.cl will not be available until further notice.

Finally, we would like to ask all depositors that were part of the rehearsal, and that conducted validations on Monday the 16th and Tuesday the 17th to send their evidence as soon as possible to conclude this stage.

Should you have any questions, please contact your executive or send us an email to: