Dear Participants,

In the context of the preparation for the market release of the new Forward Service, DCV informs that, in view of the progress of the project and the activities underway, the Company's Board of Directors has decided to change the go-live date, initially scheduled for December 2024, to the end of March 2025. DCV continues to work on optimizing the new platform's deployment process, and we will keep you informed of the evolution of this process and any eventual changes.

The following are the upcoming activities and dates prior to the service start date (day zero):

  1. Online training #2: Wednesday, December 18, 2024.
    Objective: to reinforce the contents covered in training #1 and to show pending functionalities:
    • Requests module.
    • 2-4 eyes approval.
  2. "Market Testing" Preparation: during December 2024.
    • Creation of operator and proxy users.
    • Assignment of roles (profiles).
    • Migration of proxies and framework contracts.
    • Configuration of the monitoring criteria (2 or 4 eyes).
    • Configuration and/or technical requirements.
    • All of the above in a training environment.
  3. Market Testing: January 15 through February 28, 2025.
    A set of tests with the most relevant cases will be delivered.
  4. Signing of the new forward service contract: February 20, 2025, is the deadline for signing the new contract.
  5. Data migration activities and final configuration: March 2025.
  6. Day zero: start of service, end of March 2025.

 

Should you have any questions, please send us an email to